Used to create a new work package.

Opens when you right-click Work Packages in the Work Package dialog and from the pop-up menu, select New Work Package, and then select the type of work package and the discipline.

The title bar of the dialog displays the type of work package, the discipline and the activity type, for example, Installation Work Package - Pipe Install - New.

SettingDescription
Boundary

Lists any boundaries that were created and saved.

Assign Boundary

Confirms the selection made in the Boundary field and applies the boundary to the work package.

Include components intersecting the boundary

Turn on if you want to include in the work package the components that intersect the boundary.

Assigned Boundary

Displays the name of the boundary you selected.

Selected

Displays the name of the component selected in the view.

Component List

Shows the name and type of the components included in the current work package.

Selection Level

Lists the different levels of selection. What displays in this list depends on the discipline selected.

For example, if you select Pipe in the Disciplines dialog, when you open the Work Packages - New dialog, the Selection Level displays these options:

  • Pipe Iso — Selects everything in that Pipe Iso Level, such all valves, field welds, and miscellaneous components, such as supports and support guides.

  • Component — Adds only those components that are selected.

Add

Adds the component to the work package.

Remove

Removes the component from the work package.

Task List

Displays the work package tasks to be performed before completion with budgeted hours, linear footage, and total number of tasks.

Right-click the column headings in the Task List to get the Customize Columns option. When you click this option, the Attribute Configuration dialog opens, which allows you to change the order of the columns, hide or show columns, or rename columns. Controls on this dialog are analogous to those on the Project Schedule Attribution Configuration dialog.

Unselect components after Add or Remove

When on, causes the selected component to become unselected in the 3D model after either adding it to or removing it from the work package.

Select Prev(ious)

Restores the components to the color they were before they were selected for work package inclusion.

Re-apply Color

Recolors the VCM according to the work package component status.

Color Legend

Components in the VCM are assigned the following colors in the Components dialog and the View window:

Purple

Current pack

These components are in the Work Package and are being worked on presently.

Blue

Other pack

These components already reside in a Work Package. A component can only reside in one Work Package of the same type.

Green

Not in a pack

These components have tasks associated to them and are ready to be added to a Work Package.

Gray

Not available

These components have no tasks available and cannot be added to a Work Package.

New

Opens a dialog to create a new work package.

OK

Opens a dialog that requires you to input the work package name.

Cancel

Closes the dialog without saving the changes.

Apply